RBWWTP HEADWORKS IMPROVEMENTS PROJECT

Location:

EL PASO, TX

Client:

MGC Contractors

Background

In 2019, El Paso Water outlined plans to expand the Roberto Bustamante Wastewater Treatment Plant (RBWWTP) and enhance the headworks facility to keep up with the growth in its service area. The RBWWTP, originally built in 1988 with modifications made in 2001, required improvements to address operational issues and prepare for the anticipated expansion of the facility. MGC Contractors contracted with Schnabel to provide earth retention and groundwater cutoff services to facilitate the construction of a new influent pump station. This pump station will play a major role in the wastewater treatment process at the RBWWTP.

Schnabel’s Solution

To reduce groundwater seepage from the base of the excavation, jet grouting was employed to create a seal slab. This process involves the injection of high-pressure grout into the ground through a drill string as it is rotated, creating a solid and impermeable column of treated soil. A bottom plug was created by constructing numerous overlapping columns of treated soil at the base of the excavation to cutoff water. A significant quantity of jet grouting was performed on the project, with over 6,200 cubic yards of soil being treated. This extensive application of jet grouting ensured a strong and reliable plug for the cutoff wall, effectively reducing the groundwater seepage and enhancing the overall stability and integrity of the excavation.

Tiedown anchors were installed at the base of the excavation to ensure stability and prevent potential issues such as heaving. The project included over 9,000 linear feet of tiedown anchors installed to depths of 80 feet. The tiedown anchors were installed with a crane with hanging leads with a continuous flight auger. The anchors were drilled through the jet grout plug after it was completed and reinforcing bars were used to create tensile capacity for the tiedowns.

Results

The earth retention and groundwater cutoff services provided by Schnabel at the Roberto Bustamante Wastewater Treatment Plant Headworks Improvements Project will aid in the construction of the new influent pump station. By implementing soil mixing, the influx of groundwater was reduced, contributing to the overall stability and success of the project. The application of jet grouting ensured a strong plug for the cutoff wall, effectively reducing groundwater infiltration. Additionally, tiedown anchors were installed to stabilize the bottom of the excavation. In closing, the RBWWTP Headworks Improvements Project will result in a 140% increase in plant capacity.

Quick Facts

Location

El Paso, Texas

Client

El Paso Water

Market

Water / Wastewater

Work Performed

Jet grouting & tiedowns

Completion Date

2023

Duration

--

Contract Value

--

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Lorem ipsum, consectetur adipiscing

Quick Facts

Location

Client

Market

Work Performed

Completion Date

Duration

Contract Value

El Paso, Texas

El Paso Water

Water / Wastewater

Jet grouting & tiedowns

2023

--

--

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Lorem ipsum, consectetur adipiscing

Related Projects

Key Contacts:

David Vega Sanchez | PM, Pre-Con

Key Contacts:

German Varon | Sr. PM, Pre-Con

Ernie Brandl | Sr. PM, Pre-Con

Key Contacts:

Ryan Whaley | Sr. PM, Pre-Con

Kristopher Knier | Sr. PM, Pre-Con

Brendan Sheppard | Sr. PM, Pre-Con

Key Contacts:

Claus Ludwig | Sr. PM, Pre-Con

Key Contacts:

Mark Goudschaal | Sr. PM, Pre-Con

Key Contacts:

Sue Wright | Sr. PM, Pre-Con

Harold Gathers | Sr. PM, Pre-Con

Key Contacts:

Sixto Fernandez | Mid-Atlantic Area Manager

Rich Pratt | Sr. PM, Pre-Con

Taylor Youngwood | PM, Pre-Con

Key Contacts:

Josh Fallon | Sr. PM, Pre-Con

Key Contacts:

Michael Patzek | Business Development Manager