UVA MCINTIRE SCHOOL OF COMMERCE

Location:

CHARLOTTESVILLE, VA

Client:

UVA McIntire School of Commerce Project

Background

Schnabel’s work on The UVA McIntire School of Commerce Project will facilitate the preservation and renovation of an approximately 22,000 sq. ft. four-story section of the 105-year-old Cobb Hall as well as a new 4,200 sq. ft. academic building, Shumway Hall, that will serve as a hub for UVA commerce students. Furthermore, this project will expand the amount of physical space that students have available to them by facilitating the construction of new student meeting spaces, classrooms, support service areas, labs, and more.

Schnabel’s Solution

The design of Shumway Hall required around 75% of Cobb Hall to be demolished, leaving a small portion of the building to remain. Schnabel was hired to install permanent excavation support in front of Cobb Hall to allow for the construction of Shumway Hall. The renovations planned inside the remaining Cobb Hall required underpinning existing footings. Around the remainder of Shumway Hall, temporary excavation support was required including a tunnel section to connect the new structure with the adjacent Rouss Robertson Hall.

The decision was made to install a secant wall with permanent tiebacks in front of the remaining portion of Cobb Hall to reduce potential settlements of the structure. The remaining temporary excavation support was designed as soldier piles and tiebacks except in the tunnel section, where temporary bracing would be utilized.

Results

The main challenge during construction was sequencing our work alongside the demolition and restoration of Cobb Hall, which required daily coordination between our respective field teams. The project limits were tight, and the hillside grading made movement and access difficult. Soldier and secant pile installation began during demolition and precautions were required to keep both operations at a safe distance from one another.

The project was completed in January 2023 without detrimental movements to our shoring or Cobb Hall. Special thanks to the many people involved in this project who rose above the numerous challenges and were able to get the project completed on time.

Quick Facts

Location

Charlottesville, Virginia

Client

University of Virginia

Market

Education

Work Performed

Secant wall & underpinning

Completion Date

January 2023

Duration

--

Contract Value

--

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Lorem ipsum, consectetur adipiscing

Quick Facts

Location

Client

Market

Work Performed

Completion Date

Duration

Contract Value

Charlottesville, Virginia

University of Virginia

Education

Secant wall & underpinning

January 2023

--

--

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Lorem ipsum, consectetur adipiscing

Related Projects

Key Contacts:

David Vega Sanchez | PM, Pre-Con

Key Contacts:

German Varon | Sr. PM, Pre-Con

Ernie Brandl | Sr. PM, Pre-Con

Key Contacts:

Ryan Whaley | Sr. PM, Pre-Con

Kristopher Knier | Sr. PM, Pre-Con

Brendan Sheppard | Sr. PM, Pre-Con

Key Contacts:

Claus Ludwig | Sr. PM, Pre-Con

Key Contacts:

Mark Goudschaal | Sr. PM, Pre-Con

Key Contacts:

Sue Wright | Sr. PM, Pre-Con

Harold Gathers | Sr. PM, Pre-Con

Key Contacts:

Sixto Fernandez | Mid-Atlantic Area Manager

Rich Pratt | Sr. PM, Pre-Con

Taylor Youngwood | PM, Pre-Con

Key Contacts:

Josh Fallon | Sr. PM, Pre-Con

Key Contacts:

Michael Patzek | Business Development Manager